Key Project Activities and Upcoming Events

  • SCE will convene an Aquatic Technical Working Group (TWG) WebEx on December 3, 2019 with interested stakeholders to discuss results to date and options for completing the AQ 9 – Entrainment Study. Meeting details are as follows:
    Date: December 3, 2019
    Time: 1:00 pm – 3:00 pm
    WebEx Link: https://cardno.zoom.us/j/529935364
    Join by Phone: (669) 900-6833 or (646) 876-9923
    Meeting ID: 529 935 364
  • SCE filed a Draft License Application (DLA) with the Federal Energy Regulatory Commission (FERC) on July 26, 2019 for the Kaweah Project. SCE is requesting renewal of its license to continue operation and maintenance of the Project with a license term of 50 years. Public portions of the DLA are provided below for review and download.
  • Current FERC Process Plan and Schedule
  • Register online here to be notified via e-mail of new filings and issuances related to the Kaweah Project.

Draft License Application

Kaweah Project Draft License Application (Public Information)

Volume 1: Initial Statement, Exhibits A, B, C, D, G, and H

Volume 3: Exhibit E

Volume 3: Supporting Document A

Negotiations

  • Management and Monitoring Plans

Contact Us

Name Company Project Role Address Email Phone
Wayne Allen SCE Principal Manager 1515 Walnut Grove Ave. Rosemead, CA 91770 wayne.allen@sce.com 626-302-9741
David Moore SCE Project Lead 1515 Walnut Grove Ave. Rosemead, CA 91770 david.moore@sce.com 626-302-9494
Jim Hastreiter FERC Assigned Staff   James.hastreiter@ferc.gov 503-552-2760