SCE is working to further reduce the risk of wildfire by burying power lines in high fire risk areas, especially where lines have not been replaced by covered conductor. SCE targets areas for undergrounding its power lines based on several considerations. The targeted undergrounding effort will make the electrical system more reliable during extreme weather conditions by protecting it from high winds, vegetation and other hazards that could cause fires or power outages.
Note: For undergrounding projects not related to wildfire mitigation, refer to Rule 20 undergrounding projects, which are initiated by a governmental agency (e.g., city, county), developer or individual customer.
Undergrounding Work Phases
Planning
During this phase, SCE planners and surveyors will conduct a feasibility assessment to help determine the scope of work that will take place in a selected community. They will gather data and make observations to analyze the viability of undergrounding electrical lines, which may include accessing and taking images of equipment and surrounding areas. This is a critical assessment to determine if this type of work can be completed at the proposed location.1 During the design phase, planners prioritize routes within public rights of way, but in some cases, limited access through private property (easements) may be needed.
Moving forward requires cooperation with property owners. Impacted property owners shall be informed about the upcoming project.
Permitting
Once the scope of work is established, SCE can determine if permitting is required. Most projects require at least one permit for road closures, typically from a city, county or Caltrans. Additional permit requirements depend on the project’s location. They may include state and federal land use permits, environmental clearances, or railroad rights-of-way permits. Permit approval may take as little as two months but could take significantly longer depending on individual project circumstances.
Construction
Work can be scheduled and construction can begin once all the required permits and necessary land rights are received.2 In most cases, this work will require a power outage at the end of construction, when the power is ready to be switched from the overhead to the underground lines. We will notify customers in advance if an outage is needed.
Undergrounding Work Status
Kern County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Flycatcher | Unincorporated Area (Mountain Mesa, Weldon) | 2026 |
Los Angeles County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Acapulco | Unincorporated | 2026 | ||||
| Arboretum | Arcadia | 2026 | ||||
| Avenida | Unincorporated Area (La Verne/ Claremont) | 2027 | ||||
| Brakeman | Rowland Heights | 2027 | ||||
| Clarinet | Unincorporated Area (Oak Flats, Ninetynine Oaks) | Anticipate starting construction in 2025 | Multiple Years | |||
| Cornwall | Unincorporated/ Whittier | 2027 | ||||
| Crummer | Agoura Hills | 2025 | ||||
| Cuthbert | Malibu, Unincorporated Area (Malibu Vista) | 2026 | ||||
| Devils Gate | Altadena | Expedited for fire rebuild | 2026 | |||
| Gorge | Altadena | Expedited for fire rebuild | 2025 | |||
| Guitar | Unincorporated, Santa Clarita | 2027 | ||||
| Hackberry | La Habra Heights | 2028 | ||||
| Haskell | La Canda Flintridge | 2029 | ||||
| Hillard | La Canda Flintridge | 2027 | ||||
| Horizon | Hidden Hills; Unincorporated | 2026 | ||||
| Horntoad | Calabasas, Unincorporated | 2026 | ||||
| Huckleberry | Palmdale, Unincorporated Area (Elizabeth Lake) | 2025 | ||||
| Kinneloa | Altadena | Expedited for fire rebuild | 2025/2026 | |||
| Kinsey | Unincorporated | 2027 | ||||
| Lamanda | Altadena | Expedited for fire rebuild | 2025/2026 | |||
| Maguire | Unincorporated | 2027 | ||||
| Mamba | Santa Clarita, Unincorporated | 2027 | ||||
| Maybell | Covina/ San Dimas | 2028 | ||||
| Merlin | Malibu, Unincorporated Area (Malibu Hills) | 2026 | ||||
| Milo | Calabasas | 2026 | ||||
| Mulholland | Unincorporated Area (Triunfo Canyon, Malibu Lake) | Started in 2024 | Multiple Years | |||
| Neargate | Santa Clarita | 2027 | ||||
| Nero | Santa Clarita | 2027 | ||||
| Nicholas | Malibu, Unincorporated | Expedited for fire rebuild | 2025 | |||
| Omega | La Habra Heights/Whittier | 2029 | ||||
| Orion | Santa Clarita, Unincorporated | 2027 | ||||
| Palmer | La Verne/ Claremont/ Unincorporated | 2025 | ||||
| Paloma | Altadena | Expedited for fire rebuild | 2026 | |||
| Payne | Bradbury | 2028 | ||||
| Paradise | Calabasas, Unincorporated Area (Topanga Park/Canyon) | 2026 | ||||
| Plateau | Calabasas, Unincorporated Area | 2026 | ||||
| Primrose | Monrovia | 2027 | ||||
| Python | Santa Clarita | Construction Complete | 2022 | |||
| Rhoda | Calabasas, Unincorporated Area | 2026 | ||||
| Robin/ Blue Ridge | Unincorporated, Big Pines | 2026 | ||||
| Rockhill | Hacienda Heights | 2027 | ||||
| Romanus | Unincorporated/ Near Santa Clarita | 2027 | ||||
| Seco | Altadena | Expedited for fire rebuild | 2025/2026 | |||
| Serra | Malibu, Unincorporated Area | 2026 | ||||
| Showdown | Palmdale | 2026 | ||||
| Sienna | Calabasa; Unincorporated | 2026 | ||||
| Stutz | Whittier | 2027 | ||||
| Tola | Altadena | Expedited for fire rebuild | 2026 | |||
| Triunfo | Agoura Hills/ Unincorporated Area | 2026 | ||||
| Tuna (Zuma) | Malibu, Unincorporated Area (Malibu Hills) | 2028 | ||||
| Veterans | Los Angeles, Unincorporated Area | 2026 | ||||
| Vicasa | Unincorporated Area (Topanga Canyon) | Started in 2024, Expedited for fire rebuild | Multiple Years | |||
| Whipstock | La Habra Heights/ Rowland Heights | 2028 |
Mono County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Pickle Meadows | Unincorporated Area (Near Sonora Junction) | 2027 |
Orange County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Acres | Laguna Beach, Unincorporated | 2027 | ||||
| Agate | Laguna Beach, Unincorporated | 2026 | ||||
| Artist | Laguna Beach, Unincorporated | 2026 | ||||
| Cortese | Laguna Beach | 2027 | ||||
| Kewamee | Laguna Beach, Unincorporated | 2026 | ||||
| Rubin | Irvine, Laguna Beach, Aliso Viejo | Anticipate starting construction in 2027-2028 | Multiple Years | |||
| Rustic | Unincorporated (near Rancho Santa Margarita) | 2027 |
Riverside County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Bohemia | Corona | Construction Complete | 2024 | |||
| Carancho | Unincorporated | Construction complete | 2025 | |||
| Cereal | Lake Elsinore, Unincorporated Area (Lake Elsinore) | Construction Complete | 2024 | |||
| Conestoga | Unincorporated/ near Temescal Valley | Anticipate starting construction in 2025 | Multiple Years | |||
| Dartmouth | San Jacinto, Unincorporated Area | Construction complete | 2025 | |||
| Granny Smith | Unincorporated (El Casco) | Construction complete | 2025 | |||
| Limited | Unincorporated | Construction Complete | 2024 | |||
| Stageline | Alberhill, Unincorporated | Construction complete | 2025 | |||
| Texfi | Jurupa Valley | Construction Complete | 2024 | |||
| Tin Mine/Mc Allister | Unincorporated Area (Lake Mathews) | Construction Complete | 2024 |
San Bernardino County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Abacus | San Bernardino | 2026 | ||||
| AllView | Running Springs | 2029 | ||||
| Big Falls | Forest Falls, Mountain Home Village | 2026 | ||||
| Boulder | San Bernardino/ Highland | 2025 | ||||
| Bryn Mawr | Redlands | Construction complete | 2025 | |||
| Butterfield | Chino Hills | Construction Complete | 2024 | |||
| Camp Angelus | Angelus Oaks | 2026 | ||||
| Circle | Wrightwood/ Unincorporated | Construction Complete | 2024 | |||
| Cram | San Bernardino, Unincorporated | 2026 | ||||
| Crump | Unincorporated (Forest Falls) | 2026 | ||||
| Del Carbon | Chino Hills | 2027 | ||||
| Fano | San Antonio Heights | Construction complete | 2025 | |||
| Hass | Mentone, Redlands, Unincorporated Area | 2026 | ||||
| Lark | Wrightwood | 2027 | ||||
| Mutual | Redlands | Construction complete | Multiple Years | |||
| Oak Glen | Oak Glen | 2027 | ||||
| Poultry | Forest Falls, Mountain Home Village | 2026 | ||||
| Poultry / Stonewood / Bear Valley | Yucaipa, Unincorporated Area | 2025 | ||||
| Santorini | Rancho Cucamonga | Construction Completed | 2025 | |||
| Stanwood | San Bernardino | 2027 | ||||
| Sutt | San Bernardino | Construction complete | 2025 | |||
| Tender | Chino Hills | 2026 | ||||
| Verdemont | Unincorporated | 2026 |
Santa Barbara County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Stanwood | Santa Barbara, Unincorporated | 2027 |
Tulare County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Success | Unincorporated Area (Soda Springs, Bagby Hill) | 2025 |
Ventura County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Academy | Thousand Oaks | 2027 | ||||
| Borchard | Thousand Oaks, Unincorporated | 2025 | ||||
| Dolphin | Unincorporated Area (Long Grade Canyon near CSU, Channel Islands) | Construction complete | 2025 | |||
| Hooligan | Thousand Oaks, Unincorporated Area (Hidden Valley) | 2025 | ||||
| Maguire | Unincorporated | 2027 |
Frequently Asked Questions
FAQ
- Targeted Undergrounding - General
- Targeted Undergrounding - Permitting and Easements
- Targeted Undergrounding - Construction
- Targeted Undergrounding - Claims
電線が地中化されていない場合、SCEは、裸電線を被覆導体に交換するなど、他の緩和策を追求し続けます。これは、特に検査や植生管理を行うことで補完される場合に、発火リスクを費用対効果よく迅速に低減する目的において最も価値のある手法の1つです。SCEの山火事緩和の取り組みの詳細については、sce.com/mitigationをご覧ください。
現在、山火事緩和を目的とした特定の地中化プロジェクトへの資金提供は、SCEの一般料金審査手続の一環として要請されています。これは政府機関(例:市、郡)、開発者、または個人の顧客によって開始されるルール20に基づく地中化プロジェクトとは異なります。
- Per current CPUC-approved tariff rules, customers are responsible for the cost of undergrounding service lines, which connect utility facilities to property owners’ electrical panels. These civil construction costs are typically paid to a private, licensed contractor hired by the homeowner to perform the civil work required to install an underground service line on the homeowner’s property. SCE is seeking alternative ways to help reduce this expense for these homeowners.
- At this point, there is an option for standing homes to remain with overhead service line connections with covered conductor.
現在、山火事緩和を目的とした特定の地中化プロジェクトへの資金提供は、SCEの一般料金審査手続の一環として要請されています。これは政府機関(例:市、郡)、開発者、または個人の顧客によって開始されるルール20に基づく地中化プロジェクトとは異なります。
SCEのターゲットを絞った地中化ウェブサイトでは郡別地図を提供しており、さまざまなコミュニティで計画している作業の範囲についてご覧いただけます。地中化作業ではフェーズに応じて、異なる許可が必要です。計画フェーズでは、SCEは市、郡、Caltrans(カルトランス)に対して早期に許可申請を開始します。また、政府の土地および環境に関する要件にも着手します。スケジューリングフェーズに入ると、標準的な許可および地役権の手続きを行い、環境認可手続きを実施し、必要に応じて追加の機関からの許可を取得します。地中化工事はルート全体にわたって影響を及ぼすため、複数の機関や管轄区域からの承認が必要となる場合があり、さらに詳細な審査と承認が求められることがあります。
No. An easement allows crews to access the property for construction or maintenance on SCE equipment and for that equipment to remain.
SCE will only enter the premises if equipment installation or maintenance is needed. Customers will be notified before crews arrive.
Once an agreement is reached, the easement is permanent and will stay with the property, even if the property ownership changes.
During the design phase, planners try to avoid the need for easements, but sometimes the only feasible path for underground equipment is through private property. If just one customer declines, the entire neighborhood may not be able to have underground lines.
SCE will only enter the premises if equipment installation or maintenance is needed. Customers will be notified before crews arrive.
No. An easement allows crews to access the property for construction or maintenance on SCE equipment and for that equipment to remain.
A Right of Entry (ROE) grants temporary permission to an entity, such as SCE, to enter and access a property for specific purposes (e.g., inspections, surveys or construction preparation).
An easement is a permanent property right that allows ongoing use of a portion of the property.
A Right of Entry (ROE) grants temporary permission to an entity, such as SCE, to enter and access a property for specific purposes (e.g., inspections, surveys or construction preparation). An easement is a permanent property right that allows ongoing use of a portion of the property.
地中化は非常に複雑なプロジェクトであるため、作業が進行するにつれて作業のタイミングが変更される可能性があります。作業は通常、月曜日から金曜日の午前7時から午後7時まで行われ、週末に作業が行われることもあります。地下工事の時間は同じですが、場所によっては地下掘削のために24時間の作業が必要になることがあります。
SCEの車両には会社のロゴが表示されます。作業に関わる人は誰でもIDバッジを携帯します。
ターゲットを絞った地中化作業では、個人の敷地への立ち入りが必要になる場合がありますが、事前に所有者に通知します。私たちは、交通が私たちの生活に与えるストレスを理解しています。SCEは、交通の影響に関する広報活動で市と緊密に連携し、通行止めを考慮して通勤や日常の用事を計画できるようにします。車線閉鎖の影響を完全に取り除くことはできませんが、周知を徹底することでご不便を最小限に抑えることができます。
地下工事中の粉塵を完全に排除することはできませんが、建設機械や車両の稼働中に作業現場で定期的に水を撒く水タンク車を見かけることがあるかもしれませんが、この水タンク車が浮遊粉塵の軽減に役立ちます。これはプロジェクトの粉塵制御ガイドラインに従って実施されています。工事による生活への支障を軽減するための簡単なヒントをいくつかご紹介します。工事現場に面した窓やドアを閉めて騒音やほこりを減らし、プロジェクトの最新情報を確認して、地域で行われている作業についての最新情報を常に把握してください。
地中化工事が完了した後、SCEはプロジェクト作業区域で工事後の清掃および復旧活動を実施します。
地中埋設工事中にお客様の所有物に損害が生じ、その責任がSCEにあるとお考えの場合は、申立を提出することができます。SCEの申立対応部門は、ケースバイケースで申立を評価します。申立の提出に関する詳細は、sce.com/claimsをご覧ください。
ウェブサイトで回答されていない具体的な質問がある場合は、プロジェクトチーム専用の電話ボイスメールボックス(1-888-331-0010)にボイスメールを残すことができます。
Additional Information
Contact Us
Please email us or leave a voice message for the Targeted Undergrounding project team on our dedicated phone voicemail.
Email: SCEprojects@sce.com
Phone: 1-888-331-0010
1 An assessment is only to determine the feasibility of undergrounding power lines in the areas identified. It is not guaranteed that SCE will perform this work in your community.
2 Work may be rescheduled or delayed for various reasons, including crews' need to focus on emergency repairs, outage restrictions during heat storms and the discovery of endangered species or historical artifacts on-site.