SCE is working to further reduce the risk of wildfire by burying power lines in high fire risk areas, especially where lines have not been replaced by covered conductor. SCE targets areas for undergrounding its power lines based on several considerations. The targeted undergrounding effort will make the electrical system more reliable during extreme weather conditions by protecting it from high winds, vegetation and other hazards that could cause fires or power outages.
Note: For undergrounding projects not related to wildfire mitigation, refer to Rule 20 undergrounding projects, which are initiated by a governmental agency (e.g., city, county), developer or individual customer.
Undergrounding Work Phases
Planning
During this phase, SCE planners and surveyors will conduct a feasibility assessment to help determine the scope of work that will take place in a selected community. They will gather data and make observations to analyze the viability of undergrounding electrical lines, which may include accessing and taking images of equipment and surrounding areas. This is a critical assessment to determine if this type of work can be completed at the proposed location.1 During the design phase, planners prioritize routes within public rights of way, but in some cases, limited access through private property (easements) may be needed.
Moving forward requires cooperation with property owners. Impacted property owners shall be informed about the upcoming project.
Permitting
Once the scope of work is established, SCE can determine if permitting is required. Most projects require at least one permit for road closures, typically from a city, county or Caltrans. Additional permit requirements depend on the project’s location. They may include state and federal land use permits, environmental clearances, or railroad rights-of-way permits. Permit approval may take as little as two months but could take significantly longer depending on individual project circumstances.
Construction
Work can be scheduled and construction can begin once all the required permits and necessary land rights are received.2 In most cases, this work will require a power outage at the end of construction, when the power is ready to be switched from the overhead to the underground lines. We will notify customers in advance if an outage is needed.
Undergrounding Work Status
Kern County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Flycatcher | Unincorporated Area (Mountain Mesa, Weldon) | 2026 |
Los Angeles County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Acapulco | Unincorporated | 2026 | ||||
| Arboretum | Arcadia | 2026 | ||||
| Avenida | Unincorporated Area (La Verne/ Claremont) | 2027 | ||||
| Brakeman | Rowland Heights | 2027 | ||||
| Clarinet | Unincorporated Area (Oak Flats, Ninetynine Oaks) | Anticipate starting construction in 2025 | Multiple Years | |||
| Cornwall | Unincorporated/ Whittier | 2027 | ||||
| Crummer | Agoura Hills | 2025 | ||||
| Cuthbert | Malibu, Unincorporated Area (Malibu Vista) | 2026 | ||||
| Devils Gate | Altadena | Expedited for fire rebuild | 2026 | |||
| Gorge | Altadena | Expedited for fire rebuild | 2025 | |||
| Guitar | Unincorporated, Santa Clarita | 2027 | ||||
| Hackberry | La Habra Heights | 2028 | ||||
| Haskell | La Canda Flintridge | 2029 | ||||
| Hillard | La Canda Flintridge | 2027 | ||||
| Horizon | Hidden Hills; Unincorporated | 2026 | ||||
| Horntoad | Calabasas, Unincorporated | 2026 | ||||
| Huckleberry | Palmdale, Unincorporated Area (Elizabeth Lake) | 2025 | ||||
| Kinneloa | Altadena | Expedited for fire rebuild | 2025/2026 | |||
| Kinsey | Unincorporated | 2027 | ||||
| Lamanda | Altadena | Expedited for fire rebuild | 2025/2026 | |||
| Maguire | Unincorporated | 2027 | ||||
| Mamba | Santa Clarita, Unincorporated | 2027 | ||||
| Maybell | Covina/ San Dimas | 2028 | ||||
| Merlin | Malibu, Unincorporated Area (Malibu Hills) | 2026 | ||||
| Milo | Calabasas | 2026 | ||||
| Mulholland | Unincorporated Area (Triunfo Canyon, Malibu Lake) | Started in 2024 | Multiple Years | |||
| Neargate | Santa Clarita | 2027 | ||||
| Nero | Santa Clarita | 2027 | ||||
| Nicholas | Malibu, Unincorporated | Expedited for fire rebuild | 2025 | |||
| Omega | La Habra Heights/Whittier | 2029 | ||||
| Orion | Santa Clarita, Unincorporated | 2027 | ||||
| Palmer | La Verne/ Claremont/ Unincorporated | 2025 | ||||
| Paloma | Altadena | Expedited for fire rebuild | 2026 | |||
| Payne | Bradbury | 2028 | ||||
| Paradise | Calabasas, Unincorporated Area (Topanga Park/Canyon) | 2026 | ||||
| Plateau | Calabasas, Unincorporated Area | 2026 | ||||
| Primrose | Monrovia | 2027 | ||||
| Python | Santa Clarita | Construction Complete | 2022 | |||
| Rhoda | Calabasas, Unincorporated Area | 2026 | ||||
| Robin/ Blue Ridge | Unincorporated, Big Pines | 2026 | ||||
| Rockhill | Hacienda Heights | 2027 | ||||
| Romanus | Unincorporated/ Near Santa Clarita | 2027 | ||||
| Seco | Altadena | Expedited for fire rebuild | 2025/2026 | |||
| Serra | Malibu, Unincorporated Area | 2026 | ||||
| Showdown | Palmdale | 2026 | ||||
| Sienna | Calabasa; Unincorporated | 2026 | ||||
| Stutz | Whittier | 2027 | ||||
| Tola | Altadena | Expedited for fire rebuild | 2026 | |||
| Triunfo | Agoura Hills/ Unincorporated Area | 2026 | ||||
| Tuna (Zuma) | Malibu, Unincorporated Area (Malibu Hills) | 2028 | ||||
| Veterans | Los Angeles, Unincorporated Area | 2026 | ||||
| Vicasa | Unincorporated Area (Topanga Canyon) | Started in 2024, Expedited for fire rebuild | Multiple Years | |||
| Whipstock | La Habra Heights/ Rowland Heights | 2028 |
Mono County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Pickle Meadows | Unincorporated Area (Near Sonora Junction) | 2027 |
Orange County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Acres | Laguna Beach, Unincorporated | 2027 | ||||
| Agate | Laguna Beach, Unincorporated | 2026 | ||||
| Artist | Laguna Beach, Unincorporated | 2026 | ||||
| Cortese | Laguna Beach | 2027 | ||||
| Kewamee | Laguna Beach, Unincorporated | 2026 | ||||
| Rubin | Irvine, Laguna Beach, Aliso Viejo | Anticipate starting construction in 2027-2028 | Multiple Years | |||
| Rustic | Unincorporated (near Rancho Santa Margarita) | 2027 |
Riverside County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Bohemia | Corona | Construction Complete | 2024 | |||
| Carancho | Unincorporated | Construction complete | 2025 | |||
| Cereal | Lake Elsinore, Unincorporated Area (Lake Elsinore) | Construction Complete | 2024 | |||
| Conestoga | Unincorporated/ near Temescal Valley | Anticipate starting construction in 2025 | Multiple Years | |||
| Dartmouth | San Jacinto, Unincorporated Area | Construction complete | 2025 | |||
| Granny Smith | Unincorporated (El Casco) | Construction complete | 2025 | |||
| Limited | Unincorporated | Construction Complete | 2024 | |||
| Stageline | Alberhill, Unincorporated | Construction complete | 2025 | |||
| Texfi | Jurupa Valley | Construction Complete | 2024 | |||
| Tin Mine/Mc Allister | Unincorporated Area (Lake Mathews) | Construction Complete | 2024 |
San Bernardino County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Abacus | San Bernardino | 2026 | ||||
| AllView | Running Springs | 2029 | ||||
| Big Falls | Forest Falls, Mountain Home Village | 2026 | ||||
| Boulder | San Bernardino/ Highland | 2025 | ||||
| Bryn Mawr | Redlands | Construction complete | 2025 | |||
| Butterfield | Chino Hills | Construction Complete | 2024 | |||
| Camp Angelus | Angelus Oaks | 2026 | ||||
| Circle | Wrightwood/ Unincorporated | Construction Complete | 2024 | |||
| Cram | San Bernardino, Unincorporated | 2026 | ||||
| Crump | Unincorporated (Forest Falls) | 2026 | ||||
| Del Carbon | Chino Hills | 2027 | ||||
| Fano | San Antonio Heights | Construction complete | 2025 | |||
| Hass | Mentone, Redlands, Unincorporated Area | 2026 | ||||
| Lark | Wrightwood | 2027 | ||||
| Mutual | Redlands | Construction complete | Multiple Years | |||
| Oak Glen | Oak Glen | 2027 | ||||
| Poultry | Forest Falls, Mountain Home Village | 2026 | ||||
| Poultry / Stonewood / Bear Valley | Yucaipa, Unincorporated Area | 2025 | ||||
| Santorini | Rancho Cucamonga | Construction Completed | 2025 | |||
| Stanwood | San Bernardino | 2027 | ||||
| Sutt | San Bernardino | Construction complete | 2025 | |||
| Tender | Chino Hills | 2026 | ||||
| Verdemont | Unincorporated | 2026 |
Santa Barbara County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Stanwood | Santa Barbara, Unincorporated | 2027 |
Tulare County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Success | Unincorporated Area (Soda Springs, Bagby Hill) | 2025 |
Ventura County (Updated as of 1/15/2026)
| CIRCUIT | COMMUNITIES | PLANNING | PERMITTING | CONSTRUCTION | NEXT STEPS | TARGET COMPLETION DATE |
|---|---|---|---|---|---|---|
| Academy | Thousand Oaks | 2027 | ||||
| Borchard | Thousand Oaks, Unincorporated | 2025 | ||||
| Dolphin | Unincorporated Area (Long Grade Canyon near CSU, Channel Islands) | Construction complete | 2025 | |||
| Hooligan | Thousand Oaks, Unincorporated Area (Hidden Valley) | 2025 | ||||
| Maguire | Unincorporated | 2027 |
Frequently Asked Questions
FAQ
- Целевая прокладка подземных коммуникаций — Общие сведения
- Targeted Undergrounding - Permitting and Easements
- Targeted Undergrounding - Construction
- Targeted Undergrounding - Claims
В случаях, когда линия электропередачи не прокладывается под землей, SCE продолжает применять другие меры, например, замену открытого провода на изолированный. Это один из наиболее эффективных и экономически обоснованных способов быстрого снижения риска возгорания, особенно в сочетании с инспекциями и расчисткой растительности. Подробнее об усилиях SCE по снижению риска лесных пожаров читайте на сайте sce.com/mitigation.
В настоящее время финансирование целевых проектов по прокладке подземных линий электропередачи для снижения риска лесных пожаров осуществляется в рамках процесса общего пересмотра тарифов (General Rate Case) компании SCE. Это отличается от проектов подземной прокладки, реализуемых в соответствии с Правилом 20 (Rule 20), которые инициируются органами государственной власти (например, городом или округом), застройщиками или отдельными клиентами.
- Per current CPUC-approved tariff rules, customers are responsible for the cost of undergrounding service lines, which connect utility facilities to property owners’ electrical panels. These civil construction costs are typically paid to a private, licensed contractor hired by the homeowner to perform the civil work required to install an underground service line on the homeowner’s property. SCE is seeking alternative ways to help reduce this expense for these homeowners.
- At this point, there is an option for standing homes to remain with overhead service line connections with covered conductor.
Финансирование целевых проектов по прокладке подземных линий электропередачи для снижения риска лесных пожаров запрашивается в рамках «случая применения общей ставки», который отличается от правила 20: последнее распространяется на проекты по инициативе правительственных органов (на уровне города, округа и т. д.), застройщика или индивидуального заказчика.
На нашем сайте, посвященном прокладке подземных линий электропередачи, представлены карты работ по округам.. На них показано, какой объем работ запланирован в том или ином районе. На разных этапах выполнения проекта требуются разные разрешения. Например, на этапе планирования компания SCE подает предварительные заявки на разрешения в городские или окружные органы власти и Департамент транспорта штата Калифорния (CalTrans). На этом же этапе начинается работа по подготовке проекта к исполнению требований, связанных с использованием государственных земель и заботой о природе. Переход на этап планирования сопровождается запросом стандартных разрешений и сервитутов, а также экологических и, при необходимости, дополнительных разрешений. Подземная прокладка кабеля требует вмешательства в грунт на протяжении всего маршрута, в связи с чем могут понадобиться разрешения со стороны нескольких органов и юрисдикций, а также тщательное рассмотрение проекта и длительный процесс утверждения.
No. An easement allows crews to access the property for construction or maintenance on SCE equipment and for that equipment to remain.
SCE will only enter the premises if equipment installation or maintenance is needed. Customers will be notified before crews arrive.
Once an agreement is reached, the easement is permanent and will stay with the property, even if the property ownership changes.
During the design phase, planners try to avoid the need for easements, but sometimes the only feasible path for underground equipment is through private property. If just one customer declines, the entire neighborhood may not be able to have underground lines.
SCE will only enter the premises if equipment installation or maintenance is needed. Customers will be notified before crews arrive.
No. An easement allows crews to access the property for construction or maintenance on SCE equipment and for that equipment to remain.
A Right of Entry (ROE) grants temporary permission to an entity, such as SCE, to enter and access a property for specific purposes (e.g., inspections, surveys or construction preparation).
An easement is a permanent property right that allows ongoing use of a portion of the property.
A Right of Entry (ROE) grants temporary permission to an entity, such as SCE, to enter and access a property for specific purposes (e.g., inspections, surveys or construction preparation). An easement is a permanent property right that allows ongoing use of a portion of the property.
Прокладка подземных коммуникаций — это очень сложный проект, поэтому сроки выполнения работ могут изменяться по мере их выполнения. Работы будут проводиться с 07:00 до 19:00 с понедельника по пятницу, а также иногда по выходным. Время проведения работ по прокладке подземных коммуникаций останется прежним, но в некоторых местах для подземного бурения может потребоваться круглосуточная работа.
На автомобилях SCE будет размещен логотип компании. Все, кто задействован в выполнении работ, также будут носить бэйджи, удостоверяющие личность.
Во время прокладки подземных кабелей может потребоваться временный доступ к частным территориям, однако собственников предупредят о работах заранее. Мы понимаем, что неудобства на дорогах могут повлиять на вашу повседневную жизнь. Компания SCE тесно сотрудничает с городскими службами, чтобы своевременно информировать жителей о возможных ограничениях движения. Это поможет вам заранее спланировать поездки и дела с учётом перекрытий. Полностью избежать временных неудобств не удастся, но мы сделаем всё возможное, чтобы свести их к минимуму и заранее предупредить всех, кого это коснётся.
Несмотря на то, что пыль во время подземных строительных работ не возможно полностью устранить, вы увидите автоцистерну с водой, которая периодически будет распылять воду на рабочей площадке во время работы строительной техники и транспортных средств, чтобы уменьшить количество пыли. Это делается в соответствии с рекомендациями проекта по борьбе с пылью. Вот несколько простых советов, которые могут помочь вам сократить неудобства при строительстве: закройте окна и двери, выходящие на строительную площадку, чтобы уменьшить шум и пыль, и следите за последними новостями проекта, чтобы иметь самую последнюю информацию о работах, которые ведутся в вашем районе.
После завершения работ по прокладке подземных коммуникаций представители компании SCE выполнят необходимую уборку и восстановительные работы на рабочих участках.
У клиентов может произойти отключение электроэнергии в связи с запланированными работами по прокладке подземных коммуникаций. Мы понимаем, что временные отключения могут создавать неудобства, и ценим ваше терпение. В этих случаях мы уведомим вас по телефону, текстовым сообщением, электронным сообщением или по почте не менее чем за 72 часа до отключения, чтобы вы могли принять все необходимые меры предосторожности. Однако, обратите внимание, что время может измениться по причинам безопасности. Кроме того, отключение может быть перенесено, отменено или завершено раньше, чем планировалось. Ваше уведомление будет содержать номер запланированного отключения, который вы можете ввести на нашей карте отключений, чтобы получать последние новости.
Если вы считаете, что SCE несет ответственность за ущерб, причиненный вашему имуществу в ходе подземной прокладки линий электропередачи, вы можете подать заявку на компенсацию. Отдел по работе с претензиями SCE рассматривает каждое обращение в индивидуальном порядке. Подробнее о подаче заявки вы можете узнать на сайте sce.com/claims.
Если у вас есть вопросы, на которые вы не нашли ответа на сайте, вы можете оставить голосовое сообщение команде проекта по специальному номеру: 1-888-331-0010.
Additional Information
Contact Us
Please email us or leave a voice message for the Targeted Undergrounding project team on our dedicated phone voicemail.
Email: SCEprojects@sce.com
Phone: 1-888-331-0010
1 An assessment is only to determine the feasibility of undergrounding power lines in the areas identified. It is not guaranteed that SCE will perform this work in your community.
2 Work may be rescheduled or delayed for various reasons, including crews' need to focus on emergency repairs, outage restrictions during heat storms and the discovery of endangered species or historical artifacts on-site.