Solicitation Status and Schedule
SCE launched its 2025 DAC-GT RFO on December 5, 2025. The DAC-GT RFO is currently active and will follow the schedule set forth immediately below.
| Event | Date* |
|---|---|
| DAC-GT RFO Launch | 12/05/2025 |
| DAC-GT RFO Webinar Conference | 12/16/2025 |
| Offer Submittal Deadline (to deliver the Required Offer Submittal Materials) | 01/09/2026 |
| Anticipated Date for SCE’s Offer Selection Notification | 02/20/2026 |
| Anticipated deadline for Successful Offerors to approve populated DAC PPAs | 03/13/2026 |
| Anticipated deadline for awarded Sellers to execute standard DAC contract | 04/03/2026 |
| Anticipated date for Advice Letter filing for CPUC contract approval | 05/08/2026 |
*SCE reserves the right to revise any RFO event dates listed above.
Solicitation Website
To participate in this RFO, Offerors must use the PowerAdvocate (Wood Mackenzie) Website to download and complete, review, sign, and upload – as applicable, all RFO materials requiring input, along with any additional required offer submittal materials.
The PowerAdvocate website is available at poweradvocate.com, and the Event Code is 235145. Please refer to the RFO Instructions (downloadable from the PowerAdvocate website) for detailed guidance on registering and navigating the PowerAdvocate platform.
Notifications
If you would like to be added to SCE’s distribution list for all future DAC-GT and other energy procurement solicitations, please send an email to SCEEnergyProcurement@sce.com, including your full name and your company’s name.
Regulatory Background and Purpose of SCE’s DAC-GT RFOs
As per the relevant CPUC orders (the “DAC Decisions”) identified below, SCE is directed to periodically administer DAC-GT RFOs to procure towards its DAC-GT energy needs.
Various DAC programs, including the DAC-GT, were established on June 21, 2018 via D.18-06-027. Subsequently, the following were issued: Alternate Decision Adopting Alternatives to Promote Solar Distributed Generation in DACs, D.18-10-007, dated October 11, 2018, a decision-making corrections and clarifications to D.18-06-027, and Resolution E-4999 which promotes solar energy in the DAC-Community Solar Green Tariff (“DAC-CSGT”) and DAC-Green Tariff (“DAC-GT”) programs.
Later, on October 6, 2022, the Commission issued Resolution E-5212 that modified E-4999 to include additional DAC-eligible areas.
Finally, on May 30, 2024 the Commission approved (“D.”) 24-05-065 which implements the modified DAC-GT program and ended the DAC-CSGT program. All remaining un-procured capacity originally assigned to the DAC-CSGT tariff is to be transferred to the modified DAC-GT.
Q&As – Commonly-asked and recently-asked questions, with SCE’s responses
SCE has posted Q&As to help interested parties and potential RFO Offerors in their planning processes. Additional questions can be submitted to DACPrograms@sce.com, with responses to be publicly posted.