Kaweah Project Relicensing (FERC P-298)

null

Key Project Activities and Upcoming Events

  • SCE to convene Initial Study Report Meeting
    Date: November 1, 2018
    Time: 1:00 pm - 3:00 pm
    Location: Wyndham Visalia
    Pine Room
    9000 W. Airport Drive Visalia, CA 93277
  • SCE filed Initial Study Report on October 18, 2018
  • FERC filed Study Plan Determination on October 24, 2017
  • SCE filed Revised Study Plan (RSP) on September 18, 2017
  • SCE filed Proposed Study Plan (PSP) on May 24, 2017
  • FERC filed Scoping Document 2 (SD2) on May 18, 2017.
  • FERC filed Notice of Commencement of Pre-filing Process on February 10, 2017
  • FERC filed Scoping Document 1 (SD1) on February 10, 2017
  • FERC filed Tribal Consultation Notice on January 10, 2017
  • SCE filed Pre-Application Document (PAD) on December 14, 2016
  • FERC held two scoping meetings on March 14, 2017 and a site visit on March 15, 2017. Transcripts of FERC’s scoping meeting can be found on FERC’s eLibrary here
  • Register online here to be notified via e-mail of new filings and issuances related to the Kaweah Project.