If I want to consider Added Facilities, what do I need to do?

Submitted by candace.loyads on
Priority
1
FAQ Popularity
40
FAQ Answer

To help streamline the process, please contact your SCE Account Representative or call our Local Planning Department at 1-800-655-4555.

New to SCE?  Please fill out the SCE - Turn On Service and an Account Representative will contact you.

 

LARGE LOAD QUESTIONS (typically near or greater than 6 MVA)

For large loads, there may be an economic advantage to taking service at a sub-transmission voltage (> 50kV).  The 6 MVA threshold represents an approximate limit to the amount of load that can be served from a single 12 kV or 16 kV distribution line.  Depending upon site specific conditions, it may be more economic for SCE to install sub-transmission facilities rather than a second distribution line.

Smartling languages
0
(link sends email)Share by Email
Close Icon
Choose how to access your Preferences
OR
Lookup by Account Holder
infoicon
A code will be sent to a phone number on file for the account. Make sure you are able to receive the code via the phone number or from the account holder.