How long is this undergrounding work going to take? What hours will the work take place during the day?

Submitted by Lawrence Hoi Yip on
Priority
11
FAQ Answer
Undergrounding is a very complex project, and because of that, the timing of the work is subject to change as the work progresses. Work will typically occur from 7 a.m.-7 p.m., Monday through Friday and with occasional work on weekends. The times will be the same for undergrounding work but may require 24-hour work for underground drilling in some locations.