You may transfer DA status from one account to another through any of the following:
Customer Assignment Affidavit
Allows customers to assign DA contracts to either a new ESPs or a new retail end-use customer representing similar loads at the same physical location.
Form Requirements:
A two-part declaration must be signed by both the new Customer and the ESP.
- Current location cannot be closed for more than 60 days.
- New service account at the location cannot include bundled service accounts that have been in the customer’s name for more than 90 days.
- DASR must be submitted within 60 days of the Customer Assignment Notification Acceptance by SCE.
Download the Customer Assignment Affidavit form.
Direct Access Customer Relocation Declaration
Allows customers to relocate DA load from an existing location to a new location under any one of the four available options:
- Current Location, one existing customer Premises, where the electric load of one service account (SA) is currently served under DA and New Location is the same or a different Premises from the Current Location, which has been newly acquired, or constructed, by customer at which the customer intends to relocate all, or part of its business and operations from the Current Location.
- The New Location may only consist of one SA.
- Current Location, one existing customer Premises, where the electric load of one or more SAs are currently being served under DA and New Location is the same, or a different Premises from the Current Location, which has been newly acquired, or constructed, by customer at which the customer intends to relocate all, or part of its business and operations from the Current Location.
- The New Location may consist of one or more SAs at a single Premises.
- Current Location, one or more existing customer Premises, where the electric load of one or more SAs is currently being served under DA and New Location is a different Premises from the Current Location to which the customer intends to relocate all, or part of its business and operations from the Current Location.
- The New Location may consist of one or more SAs at a single or multiple locations after the relocation has been completed and is limited to loads the same as, or substantially the same as, the loads represented by the Current Location.
- Current Location, one or more existing customer Premises, where the electric load of one or more SAs is currently being served under DA and New Location is a different Premises that the Current Location to which the customer intends to relocate all, or part of its business and operations from the Current Location.
- The New Location - 1 Service Account (SA) per existing bundled service account; will not be eligible for DA service until SA(s) under the same customer of record at the Current Location have been terminated.
- Customer must submit this request to SCE no later than 90 days from the date all SAs at the Current Location have been terminated.
Form Requirements:
A two-part declaration must be signed by both the customer and the ESP.
- Total DA load as a result of the relocation cannot exceed the load limitations provided in the agreement.
- Current location cannot be closed for more than 60 days.
- New location cannot include bundled service accounts that have been in the customer’s name for more than 90 days (not applicable to option D above).
- DASR must be submitted within 60 days of either a) the relocation declaration’s acceptance by SCE, or b) establishment of electric service at the New Location.
Download the Direct Access Customer Relocation Declaration form.
Direct Access Customer Replacement Declaration
Allows customers to, in the normal course of business, refurbish, reconstruct, or remodel facilities at the Current Location and continue to serve these facilities under Direct Access (DA) at the Current Location, which represents one existing customer site where the electric load of one customer account is currently being served under DA.
Form Requirements:
A two-part declaration must be signed by both the customer and the ESP.
- Current service account at the location cannot be closed for more than 60 days.
- New service account at the location cannot include bundled service accounts that have been in the customer’s name for more than 90 days.
- DASR must be submitted within 60 days of the replacement declaration’s acceptance by SCE.
Download the Direct Access Customer Replacement Declaration form.
Each party's declaration must be completed and submitted by email to SCE, Customer Choice Services at ESPSUPT@sce.com. Please note that original documents must be received by SCE within 10 calendar days from the date of the fax. Original documents must be mailed to the following address:
Customer Choice Services
6060 N. Irwindale Avenue, Suite J
Irwindale, CA 91702