10/11/21 Update: Restorations will be done on Tuesday 10/12 except for the final grind & cap. This restoration includes removing all fencing and K-rail. Second St. will continue to be closed per the approved Traffic Control Plan until the grind and cap is done – estimated 10/19. The striping is schedule for 10/26.
9/22/21 Update: Please be informed that the following are the construction activities for the upcoming weeks.
- On September 24th the worksite area will extend slightly on 2nd Street to accommodate the crane to place the new vault in place.
- A lane closure will be in effect on Hermosa Avenue on Friday September 24th to allow for delivery and crane work to install the new vault.
- A street closure will be in effect on Friday September 24th for Beach Drive from 8 AM to 12 PM to allow for the crane work on placement of the new SCE vault.
- Possible extended work hours until 7:30PM will take place on Monday, September 27th to complete the vault work prior to SCE electrical work.
- SCE planned outage will take place on Tuesday September 28th from 10 PM to 5AM. Notification of the outage will be delivered by SCE to the affected residents.
- Dewatering will continue until Wednesday September 29th, with a lane closure taking place on Hermosa Ave on September 29th and 30th for the removal of the dewatering filtration equipment.
- Paving operations on 2nd street will take place on October 20th.
- Pavement striping will take place on October 27th.
Working hours will be from 8:00 am to 5:00 pm, Monday through Friday with October 30th estimated project completion.
9/15/21 Update: The work will include a generator and pump removing water from the excavation for approximately 1 week. The generator and pumps will run 24 hours a day to get the project done as quickly as possible starting on Monday 9/20 at 8:00 a.m. The generator and pumps will be protected with sound blankets to reduce noise.
9/8/21 Update: On September 13, 2021, W. A. Rasic Construction Co., Inc. will be continuing the project.
- This work will include a generator and pump removing water from the excavation for approximately 1 week. The pump and generator will produce some noise but it will be contained with blankets and fence to minimize the noise.
- The crosswalk on the South side of 2nd and Hermosa will be closed for approximately 2 weeks during this construction.
- There will be a Southern California Edison Security Guard onsite 24/7 during the construction to insure the safety of residents and the Electrical lines.
Working hours will be from 8:00 am to 5:00 pm, Monday through Friday with October 30th estimated project completion.
8/17/21 Update: Prior to conducting repair work, SCE performs routine and discreet excavations, called potholing, to ensure the location of our underground facilities. During the potholing, SCE did not run into the water table. Unfortunately, upon excavation of the vault, SCE ran into a water table issue. After reviewing the amount of water and where it is to be discharged, a permit was required from the LA Regional Water Quality Control Board, which was received on Aug. 2, 2021.
A Flood Access Permit from LA County will also be needed, which can take up to 4 to 6 weeks (SCE expects to receive the permit at the end of August). Once the permit is received, SCE and its contractor W.A. Rasic anticipates making repairs shortly thereafter. SCE is working to expedite project completion and estimates approximately 40 to 45 days to finish the project after the County permit is received.
SCE staff plans to attend the Hermosa Beach City Council meeting on Sept. 14, 2021 to provide an update on the project status and to answer questions.