Improving Reliability in Western Riverside County
Alberhill System Project
The Alberhill System Project is a major energy infrastructure investment designed to support growing electricity demand in western Riverside County while improving reliability, resilience, and operational flexibility for the region’s electric system.
The project will help strengthen system connections and enable the transfer of electrical load between systems, supporting reliable service for customers across a rapidly growing area.
Project facilities are located in unincorporated Riverside County and within the cities of Lake Elsinore, Wildomar, and Menifee, as well as nearby communities including the Temescal Valley.
The Alberhill System Project includes:
- New Alberhill Substation
Construction of a 500/115 kilovolt (kV) substation to support increased system capacity. - 500 kV Transmission Connections
Two new 500 kV transmission line segments connecting the new substation to SCE’s existing Serrano–Valley 500 kV transmission system. - 115 kV Sub-Transmission Improvements
- One new 115 kV sub-transmission line
- Modifications to four existing 115 kV lines
These upgrades will allow multiple existing substations to be served from the new Alberhill facility.
- Telecommunications Infrastructure
Installation of telecommunications systems to integrate the project into SCE’s grid operations.
The project is intended to:
- Address increasing electricity demand in western Riverside County
- Improve system reliability and resiliency under a range of operating conditions
- Enhance operational flexibility by enabling load transfers between systems
- Support continued population and economic growth in the region
The project is also expected to strengthen electric service for a large portion of the region’s population, including communities experiencing sustained growth.
| Start Construction | Finish Construction | |
|---|---|---|
| Alberhill Substation Construction | Q3 2026 | Q4 2029 |
| Transmission Line Construction | Q3 2027 | Q4 2029 |
Current Status: Approved by the California Public Utilities Commission (CPUC)
Key Milestones
- March 19, 2026: the CPUC issued a decision granting Southern California Edison a Certificate of Public Convenience and Necessity (CPCN) for the Alberhill System Project.
- September 2009: SCE filed initial application (A.09-09-022)
- 2016–2017: Environmental review completed, including Draft and Final Environmental Impact Reports (EIR)
- August 2018: CPUC issued initial decision; proceeding remained open for additional analysis
- 2020–2023: SCE filed amended applications and supplemental environmental and technical analyses as directed by the CPUC
- June 2024: CPUC issued an Addendum to the Final EIR reflecting updated project refinements [ia.cpuc.ca.gov]
- March 19, 2026: CPUC approved the project and granted CPCN
- City of Lake Elsinore
- City of Wildomar
- City of Canyon Lake
- City of Menifee
- City of Perris
- Areas of Unincorporated Riverside County including Temescal Valley
Historical Activity and Background
Previously Held Webinars
In 2018, SCE hosted two public workshops to educate the community and gather feedback on the proposed Alberhill System Project, following a request from the California Public Utilities Commission (CPUC) to provide additional information and analysis to the public. The workshops presented an overview of the project and underlying system needs, outlined next steps in the regulatory process, and solicited input on potential alternatives for further consideration. Project maps and supporting materials were made available, and subject matter experts were on hand to answer questions and engage with attendees. Both workshops were held on November 13, 2018—one in the morning at the Lake Elsinore Cultural Arts Center (183 North Main Street, Lake Elsinore, CA) from 10:00 a.m. to 12:00 noon, and a second in the evening at the Menifee Lakes Country Club (29875 Menifee Lakes Drive, Menifee, CA) from 4:30 p.m. to 7:30 p.m.
- Alberhill Webinar Q & A Responses – April 30, 2021
- Alberhill Project Webinar - April 30, 2021
- Alberhill Webinar Q&A Responses – February 20, 2020
- Alberhill Project Update Webinar - February 20, 2020
- Alberhill Webinar PowerPoint – February 20, 2020
- Alberhill Skype Broadcast for Data Package 1
- Project Webinar - May 23, 2019
With CPUC approval in place, SCE can move forward with planning and construction for the Alberhill System Project once remaining pre-construction requirements are completed. The project is expected to be in service later this decade, and SCE will continue to share public updates as work progresses.
Southern California Edison (SCE)
General Project Information:
Toll-free hotline: (866) 785-7057 extension 1
California Public Utilities Commission (CPUC)
San Francisco Public Advisor: (415) 703-2074 or public.advisor@cpuc.ca.gov
Toll-free: (866) 849-8391
Members of the news media may reach us: News-media line: News@sce.com, (626) 302-2255.