Long Beach Update

As of 9:13 a.m. today, power has been restored to all customers in Long Beach, however some customers who have been on generator power may experience temporary outages as we connect them to the network as safely as possible.

We thank customers for their patience as we work to restore them to the network as safely and efficiently as possible. We encourage customers in Long Beach to make every effort to conserve use of electricity as we continue to return the system to its full operational capacity.

We have opened our distribution center at 925 Locust at 8 a.m. today to distribute food, ice and water. The safety of the public and our crews remain our highest priority. We thank the city of Long Beach for its cooperation and for the especially important safety efforts of first responders in the Long Beach Fire and Police departments. Get the latest update >

Sandlot Substation Project (formerly Water Valley)

More Solar Power For Southern California

We’re committed to California’s renewable-power goals, and the Sandlot Substation Project near Harper Lake, in San Bernardino County, is designed to help. This project, formerly called the Water Valley Substation Project, will help us connect the Abengoa Mojave Solar Project to our electricity grid.

Neighboring Communities

San Bernardino County:  Barstow, Adelanto, Victorville

Project Details

The Sandlot Substation (formerly Water Valley) Substation Project consists primarily of:

  • Sandlot Substation: a new 220 kV substation occupying approximately 10 acres of land on the Abengoa Mojave Solar Project site.
  • Transmission Lines: Two parallel transmission line segments to connect the substation to the existing Coolwater-Kramer No. 1 220 kV transmission line.
  • Telecommunications: New facilities to connect the project to our existing telecommunications system, including 85 miles of new fiber optic communication cables on existing transmission line poles and on seven replacement poles, constructing new interest poles, placing segments of cable in existing underground conduit, and placing cable in new underground conduit.

Status

Construction on the project is complete.

Project Timeline

  • May, 2011: We filed an application with the CPUC for project approval
  • July, 2011: Approval by the CPUC
  • April, 2012: Construction began
  • June 2013: Project is complete and operational

Contact Information

If you have questions or comments about this project, contact our local staff.

From San Bernardino County:

Beverly Powell
Region Manager
1-909-307-6742
Beverly.Powell@sce.com

From Barstow or Victorville:

Nancy Jackson
Region Manager
1-760-951-3160
Nancy.Jackson@sce.com

From Adelanto:

Jennifer Menjivar
SCE Region Manager
1-760-951-3295
Jennifer.Menjivar@sce.com

Interested in working with SCE as a supplier? Learn more.