How to Submit a Claim to SCE

If you have suffered a loss or damage due to recent service interruption, and believe we may be responsible, you may submit a claim. How to submit your claim >

We investigate and evaluate each claim individually, and our policy is to respond promptly.

Long Beach Update

At this time, the majority of customers have been restored. We will attempt to restore power to most of the 260 affected customers between 6:00PM and 10:00PM. Approximately 60 customers will remain without power overnight. The distribution center at Cesar Chavez Park will be open until midnight to pass out water, ice and flashlights, and will re-open at 8:00AM tomorrow.We encourage customers in Long Beach to make every effort to conserve use of electricity today as we continue to return the system to its full operational capacity. The safety of the public and our crews remain our highest priority. We thank the city of Long Beach for its cooperation and for the safety efforts of first responders in the Long Beach Fire and Police departments. Get the latest update >

San Joaquin Cross Valley Loop Transmission Project

Delivering Clean, Hydroelectric Power to the Southern San Joaquin Valley

As one of the fastest-growing regions in California, Tulare County needs greater capacity for power transmission. This transmission project is designed to deliver cleaner, hydroelectric power from our Big Creek facilities to areas in the Southern San Joaquin Valley where demand on the rise.

Neighboring Communities

Tulare, Visalia, Hanford, Exeter, Farmersville, Woodlake, and surrounding areas of Tulare and Kings counties

Project Details

The San Joaquin Cross Valley Loop project will upgrade existing transmission lines to meet increased demand for electricity in the southern San Joaquin Valley.

Status

Project is complete. The San Joaquin Cross Valley Loop Project was energized in November 2014. Restoration activities and biological surveys are currently being conducted.

Project Timeline

  • July, 2010: Project approved by CPUC
  • 2010 to 2012: Environmental and land surveys for final engineering of project
  • March, 2012: Construction of laydown yards
  • July, 2012 : Start of site preparation in existing north-south transmission corridor
  • August, 2012:Start demolition of existing towers and rebuild as double circuit 220 kV line
  • Ongoing demolition of existing structures and installation of new structures in the existing (North-South) transmission corridor.
  • 2nd Quarter 2013: anticipate installation of new structures in the new (East-West) transmission corridor

Contact Information

If you have questions about this project, please call our toll-free project hotline at 1-866-521-8881 or contact our local staff.

William Delain
Region Manager
1-559-685-3213
William.Delain@sce.com

Interested in working with SCE as a supplier? Learn more.

Maps, Resources & More Information

Resources



For More Information