How to Submit a Claim to SCE

If you have suffered a loss or damage due to recent service interruption, and believe we may be responsible, you may submit a claim. How to submit your claim >

We investigate and evaluate each claim individually, and our policy is to respond promptly.

Long Beach Update

As of Friday night, we have restored service to most of the 260 customers that were without service by connecting generators. The handful of remaining customers will be without power overnight. Unfortunately, some locations are not able to be connected to generators because of equipment issues at the building or the location's accessibility. Our crews have made significant progress conducting detailed inspections on more than 300 vaults. As of 10 pm, 94% of these inspections have been completed. Once inspections are complete, the results will be analyzed and a network remediation plan will be developed. We continue to make repairs on the equipment. We encourage customers in Long Beach to make every effort to conserve use of electricity as we continue to return the system to its full operational capacity. The safety of the public and our crews remain our highest priority. We thank the city of Long Beach for its cooperation and for the safety efforts of first responders in the Long Beach Fire and Police departments. Get the latest update >

Eldorado-Ivanpah Transmission Project

Delivering More Solar Power For Southern California

We’re committed to California’s renewable-power goals, and the Eldorado-Ivanpah Transmission Project near the California – Nevada border will deliver up to 1,400 mW of new renewable power, including nearly 400 mW of solar power from BrightSource Energy’s Ivanpah Solar Project.

Neighboring Communities

  • San Bernardino County, California
  • Clark County, Nevada

Project Details

  • Construction of a new 220/115 kV substation in San Bernardino County, California
  • Replacing a portion of an existing 115 kV line with a 35-mile double-circuit 220 kV transmission line, which will connect to the Eldorado Substation, near Boulder City, Nevada
  • Installation of new telecommunications and distribution lines to support the project

Status

Project completed and in-service.

Project Timeline

  • March, 2012: Start of telecommunication construction
  • July, 2012: Construction of Ivanpah Substation was expected to begin
  • August, 2012: Removal of existing 115 kV transmission line; construction of 220 kV transmission line to begin
  • July 1, 2013: Project completed and in-service

Contact Information

If you have questions or comments about this project, please call our Transmission Projects Information Line at 1-866-464-2005.

Interested in working with SCE as a supplier? Learn more.