Targeted Undergrounding: Topanga Canyon Blvd (Vicasa Circuit)

Why are we performing this project?

SCE is working to further reduce the threat of wildfire by burying power lines in high-risk areas. The targeted undergrounding effort will make the electrical system more reliable during extreme weather conditions by increasing protection from high winds, vegetation, and other hazards that could cause fires or power outages. We understand this work may impact you and we thank you for your understanding. For more information about SCE’s Targeted Undergrounding (TUG) program, visit www.sce.com/tug.

This project page will be updated and maintained through the life cycle of this project to keep you informed. For additional information on this project, you may connect with us at sceprojects@sce.com. Please reference the name of this project in your email.

 

This project segment will underground approximately 4.71 miles of cable in 2024-2025. Once construction begins road closures and/or encroachments may be necessary to complete the work safely and as quickly as possible.

SCE will continue to work with elected officials and community leaders to ensure transparency, a regular cadence of communication and the safe delivery of power to your community.

Work Periods

Work is expected to be performed

  • Mon.-Fri. at 9:00 AM – 3:30 PM
  • Saturdays at 9:00 AM – 3:30 PM

Public Safety Consideration

Work will be primarily focused along TOPANGA CANYON BLVD. This will work will require heavy equipment and may call for temporary road closures or encroachments. Flaggers will be posted to safely direct traffic through this primary thoroughfare.

Please adhere to temporarily posted traffic regulations and yield to directions from the field crews. Doing so will ensure your and crew safety.

Additional Resources

Dear Neighbor Letter

  • For the next 2 weeks we will be working between 3400 Topanga Canyon Blvd and 1942 North Topanga Canyon Blvd.
  • We have installed 20 structures (Vaults and Manholes) and have 11 remaining for the entire project. We will install an additional 6 structures between 11-19 -11-26 leaving the total remaining at 5
  • 1 pull box has been installed and 5 pending to complete entire project.
  • Civil completion percentage 56.21%
  • Trench completed 12,016
  • Trench remaining 9,362