Estimated Total M-438 Services Costs
(Amounts based on available data at the time of posting)
($ x 1,000)
| Operating Month | M-438 Service Cost (Based on the operating month in which costs were incurred) |
|---|---|
| May 2005 | $400.3 |
| June 2005 | $4,618.9 |
| July 2005 | $5,376.8 |
| August 2005 | $7,297.5 |
| September 2005 | $5,396.6 |
| October 2005 | $244.7 |
| November 2005 | $0 |
| December 2005 | $0 |