Our residential customers will not be disconnected for non-payment when temperatures above 100 degrees are forecast in a 72-hour look-ahead period. During the heatwave, here are some tips to stay cool and conserve energy. Cooling center locations and hours are listed here: Find a Cooling Center. You can also call 2-1-1 for a cooling center near you.

Non-Interference Letter Requests

NON-INTERFERENCE LETTER REQUESTS

We require that you send us a Cover Letter stating that you are requesting a Non-Interference Letter with your email address, mailing address, and contact information along with the following supporting information:

  1. Property Street Address and Assessor Parcel Number(s)
  2. One copy of the project map (Tentative Tract Map, Parcel Map, etc.)
  3. Specifically, provide the city/county info and if required, the name and address of the City/County representative that may need a copy.  
  4. Please only send Adobe PDF files (no other types of attachments).

Please email to:

Southern California Edison Co.

Jeff.Clark@sce.com

The Subdivision Map Act (CA Gov Code 66436) provides 30 days for utilities to review and respond once we have received the complete package.

Thank you,

Jeff Clark

(909) 274-1078