The San Joaquin Cross Valley Loop project will upgrade existing transmission lines to meet increased demand for electricity in the southern San Joaquin Valley.
[/showmore
Status
[showmore showmore_label="Show more" showless_label="Show less"]
Project is complete. The San Joaquin Cross Valley Loop Project was energized in November 2014. Restoration activities and biological surveys are currently being conducted.
Project Timeline
- July, 2010: Project approved by CPUC
- 2010 to 2012: Environmental and land surveys for final engineering of project
- March, 2012: Construction of laydown yards
- July, 2012 : Start of site preparation in existing north-south transmission corridor
- August, 2012:Start demolition of existing towers and rebuild as double circuit 220 kV line
- Ongoing demolition of existing structures and installation of new structures in the existing (North-South) transmission corridor.
- 2nd Quarter 2013: anticipate installation of new structures in the new (East-West) transmission corridor