Southern California Edison (SCE) has begun the relicensing process for the Kern River No. 1 Hydroelectric Project (Project) (P-1930). Please use this page to find out how to get involved and stay up to date.
Below are links to Project-related materials, notifications, and documentation (provided as PDFs). All documents related to the Project can also be found on FERC’s eLibrary. This page will be updated throughout the relicensing process as new materials become available or are updated.
Recreation Use Studies
As outlined in the Recreation Technical Study Plans (refer to the Relicensing Documents section below for more information), SCE, in collaboration with the U.S. Forest Service, is soliciting input from Kern River Day users to better understand recreation use in the Project area. These recreation studies are part of the FERC relicensing process. The surveys provided below will be available to complete at day use areas and at Project trail heads in early 2025.
Thank you in advance for your participation.
Recreation Facility Use
Whitewater Boating
Maps:
In addition, surveys and QR codes will be provided at onsite survey boxes at recreation facilities and trails in the Project area.
Relicensing Overview
SCE’s operating license for the Project, FERC Project No. 1930, expires on May 31, 2028. Consequently, SCE is taking the initial steps required by the Federal Power Act and the Federal Energy Regulatory Commission (FERC) to obtain a new license for the Project using the Integrated Licensing Process (ILP) (see SCE's Relicensing Notice here).
As required by the ILP, SCE prepared the Notice of Intent (NOI) and Pre-Application Document (PAD) five years before expiration of the existing license, on May 5, 2023.
General Project Information
The Project is located on the Kern River approximately 15 miles east of the City of Bakersfield in Kern County, California. The Project is operated in a run-of-river mode. Water from the Kern River is diverted at Democrat Dam into a 9-mile-long flowline to the Project powerhouse which has a dependable generating capacity of 24.8 megawatts (MW). All Project facilities are located on National Forest Service lands within the Sequoia National Forest.
Relicensing Documents
All documents related to the Kern River No. 1 Hydroelectric Project can be found on FERC’s eLibrary. Links to relevant documents can also be accessed below.
- Table of Contents
- Cover Letter and Notice of Intent
- Section 1.0 Introduction
- Section 2.0 Existing Project Location, Facilities, and Operations
- Section 3.0-3.8 Existing Resource Information
- Section 3.9-3.15 Existing Resource Information
- Section 4.0 Preliminary Issues, Draft Technical Study Plans, and Relevant Plans
- Section 5.0 Summary of Contacts
- Appendix A. Relicensing Process Plan
- Appendix B. Summary of Contacts
- Appendix C. Draft Technical Study Plans
- Updated Draft Technical Study Plans
- AQ 1 Hydrology Technical Memo
- AQ 2 Water Quality and Water Temperature Interim Technical Memo
- AQ 3 Fish Population Interim Technical Memo
- CUL 1 Built Environment Interim Technical Memo
- CUL 2 Archaeology Interim Technical Memo
- TRI 1 Tribal Resources Interim Technical Memo
- LAND 1 Road and Trail Condition Assessment Technical Memo
- LAND 2 Erosion and Sedimentation Technical Memo
- REC 1 Recreation Facility Condition Assessment Technical Memo
- REC 2 Recreation Facility Use Assessment Interim Technical Memo
- REC 3 Whitewater Boating Interim Technical Memo
- TERR 1 Botanical Resources Interim Technical Memo
- TERR 2 Wildlife Resources Interim Technical Memo (updated May 2025)
- EJ 1 Environmental Justice Technical Memo
- Cover Letter
- Att. A: Distribution List
- Att. B: Technical Study Plan Implementation Summary
- Att. C: Revised Technical Study Plan Implementation Schedule
- Att. D: AQ 1 – Hydrology Technical Memo
- Att. E: AQ 2 – Water Quality/Water Temperature Interim Technical Memo
- Att. F: AQ 3 – Fish Population Interim Technical Memo
- Att. G: CUL 1 – Built Environment Interim Technical Memo
- Att. H: CUL 2 – Archaeology Interim Technical Memo
- Att. I: TRI 1 – Tribal Resources Interim Technical Memo
- Att. J: LAND 1 – Road and Trail Condition Assessment Technical Memo
- Att. K: LAND 2 – Erosion and Sedimentation Technical Memo
- Att. L: REC 1 – Recreation Facility Condition Assessment Technical Memo
- Att. M: REC 2 – Recreation Facility Use Assessment Interim Technical Memo
- Att. N: REC 3 – Whitewater Boating Interim Technical Memo
- Att. O: TERR 1 – Botanical Resources Interim Technical Memo
- Att. P: TERR 2 – Wildlife Resources Interim Technical Memo
- Att. Q: EJ 1 – Environmental Justice Technical Memo
Upcoming Meetings
There are no upcoming meetings.
Meetings Materials & Notices
- November 14, 2023, Proposed Study Plan Meeting Presentation
- Kern River No. 1 Hydroelectric Project Relicensing FERC Project No. 1930 – Notice of Rescheduled Stakeholder Meeting
- June 13, 2023, Stakeholder Meeting Presentation
- August 1 2023, FERC Site Visit Booklet
- FERC August 2 2023, Scoping Meeting PP Presentation
- SCE_August 2 2023, Scoping Meeting PP Presentation
- August 2, 2023, FERC Scoping Meetings Transcript
- Initial Study Report Meeting Notification
- March 19, 2025 Initial Study Report Meeting Agenda
- March 19, 2025 Initial Study Report Meeting Presentation
Technical Working Groups (TWG)
SCE would like to invite you to participate in the Kern River No. 1 Hydroelectric Relicensing Technical Working Group (TWG) meetings organized by the following resource areas:
- Aquatics
- Cultural
- Land
- Recreation
- Terrestrial
The TWG meetings are intended to obtain input on the content of the draft Technical Study Plans provided in SCE’s Pre-Application Document, dated May 2023. The meetings are open to federal and state resource agencies, local governments, Native American Tribes, non-governmental organizations, and other interested parties. Participants are expected to prepare for and attend meetings, review documents, and provide technical input to SCE and its consultants on methods, analysis, reporting, and scheduling. Considering this time commitment, it is expected that the TWG process will attract a relatively small number of subject matter experts. SCE will also support a concurrent but separate outreach effort to provide information about the relicensing to the interested public, as well as stakeholders electing not to participate in the TWG process, via electronic communication and updates to the Project website www.sce.com/kr1.
The TWG meeting schedule can be found below.
To be included in the TWG meetings, please complete the Technical Working Group Sign-up Form. If you are unable to attend a meeting, please provide comments by email to Kendra Ryan Kendra.ryan@stantec.com
.
TWG Materials
Below are links to TWG-related documentation (provided as PDFs). These links will be updated throughout the relicensing process as new materials become available or are updated.
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
AQ 1 – Hydrology AQ 2 – Water Quality/Water Temperature AQ 3 – Fish Population | July 7, 2023 10 am- 12 pm | -- |
July 31, 2023 1-3 pm | -- | |
August 24, 2023 1-3 pm | -- |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
AQ 1 – Hydrology AQ 3 – Fish Population | August 8, 2024 10 am-11:50 am | SCE_KR1_Aquatics TWG Agenda_882024 Kern River No. 1 AQ1 AQ3 TWG |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
CUL 1 – Built Environment CUL 2 - Archaeology TRI - Tribal | June 29, 2023 1-3 pm | KR1 Reliscensing Cultural Tribal TWG Meeting Information |
July 27, 2023 1-3 pm | -- | |
August 29, 2023 1-3 pm | -- |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
-- | December 3, 2024 10:30-4:30 pm | KR1 Site Visit Booklet.pptx |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
LAND 1 – Road and Trail Condition Assessment LAND 2 – Erosion and Sedimentation | June 28, 2023 1-3 pm | 2.0_Project_Location_Facilities_and_Operations_PAD_4.25.23_KR |
July 26, 2023 1-3 pm | -- | |
August 23, 2023 1-3 pm | -- |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
REC 1 – Recreation Facility Condition Assessment REC 2 – Recreation Facility Use Assessment REC 3 – Whitewater Boating | July 12, 2023 1-3 pm | KR 1_TWG_Agenda Recreation-July 12 2023 PPT_KR1_TWG_Recreation_ July_11_2023_PS |
August 10, 2023 1-3 pm | -- | |
September 6, 2023 1-3 pm | -- |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
-- | December 5, 2024 11-12 pm | PPT_KR1_TWG_Recreation_Dec_5_2024_PS_v.2.0.ppt |
Resource Area / Technical Study Plan | Technical Working Group | Related Documents |
---|---|---|
TERR 1 – Botanical TERR 2 - Wildlife | July 11, 2023 1-3 pm | -- |
August 8, 2023 1-3 pm | -- | |
September 7, 2023 1-3 pm | -- |
Contact Us
Name | Project Role | Address | Phone |
---|---|---|---|
Wayne Allen SCE | Principal Manager | 1515 Walnut Grove Ave. Rosemead, CA 91770 | 626-302-9741 |
Martin Ostendorf SCE | Senior Manager | PO Box 100 54170 Mtn Spruce Road, P.O. Box 100 Big Creek, CA 93605 | 559-893-2033 |
Meg Richardson SCE | Licensing Manager/Project Lead | 1515 Walnut Grove Ave. Rosemead, CA 91770 | 626-238-2902 |
Dan Keverline SCE | Senior Manager-Operations and Maintenance | Kern 3 Hydro Powerhouse Kernville, CA 93238 | 760-376-3813 |
Jess Fefer FERC | Assigned Staff | -- | 202-502-6631 |
Stay Informed
Please complete the Contact Registration Form if you are interested in participating in the relicensing proceeding. This will ensure you are included on the distribution list and will receive future relicensing proceeding communications and meeting notifications.
Register online to be notified via e-mail of new FERC filings and issuances related to the Project. Follow the online instructions and subscribe to docket number P-1930.
If you are unable to access information contained on this webpage, please contact Kendra Ryan at Kendra.ryan@stantec.com
- Big Creek Hydro Licensing
- Bishop Creek Project Relicensing
- Borel Project Surrender (FERC P-382)
- Kaweah Hydroelectric Project Relicensing
- Kern River No. 3 Hydroelectric Project (FERC No. 2290)
- Lee Vining Hydroelectric Project (FERC No. P-1388)
- Lundy Hydroelectric Project (FERC No. P-1390)
- Rush Creek Project Relicensing (FERC P-1389)
- FERC Standards of Conduct
- SCE Tariff Books
- Advice Letters
- SCE Manuals
- SCE Affiliate Notices
- Energy Efficiency Filings
- FERC Open Access Information
- SCE Load Profiles
- Renewable and Alternate Power
- M-438 Service Costs
- NERC Regulatory Information
- Regulatory Document Library
- Hydro Licensing
- EPIC
- E-5105 Data Documents
- Annual Reports on Electric Line Extension Expenditures
- Open Proceedings
- Energy Data - Reports and Compliance
- USWAG Notification
Reference Documents
FERC Relicensing Process
- Hydropower Licensing – A Guide for the Public
- Integrated Licensing Process (ILP)
- FERC ILP Process Chart
- Ideas for Participating in the ILP Process