How to Submit a Claim to SCE

If you have suffered a loss or damage due to recent service interruption, and believe we may be responsible, you may submit a claim. How to submit your claim >

We investigate and evaluate each claim individually, and our policy is to respond promptly.

Long Beach Update

As of 4:30 a.m. Saturday, we have restored service to approximately 190 of the 260 customers that were without service by connecting generators. We are continuing to place generators in areas that do not have power and expect to have all customers restored to service by Saturday afternoon. SCE will re-open its distribution center at Cesar Chavez community center at 8 a.m. Saturday to distribute ice and water. There are currently 10 generators in place serving businesses and residents. As the underground network system is restored, we will transition these customers off the generators. When this happens, they will experience a short power outage, which could last up to 45 minutes. We encourage customers in Long Beach to make every effort to conserve use of electricity as we continue to return the system to its full operational capacity. The safety of the public and our crews remain our highest priority. We thank the city of Long Beach for its cooperation and for the safety efforts of first responders in the Long Beach Fire and Police departments. Get the latest update >

Moorpark-Newbury 66 kV Subtransmission Line Project

Providing Long Term Reliability To Our Customers

The Moorpark-Newbury 66 kV Subtransmission Line Project will ensure the availability of reliable electric service to meet our customers’ needs in portions of Thousand Oaks and adjacent areas of unincorporated Ventura County.

Neighboring Communities

Thousand Oaks, Moorpark, and unincorporated Ventura County.

Project Details

The Moorpark-Newbury project consists of constructing a new nine mile segment of 66 kV subtransmission line between Moorpark Substation in Moorpark and Newbury Substation in Thousand Oaks. It involves both the construction of new facilities and replacement and reconductoring (rewiring) of existing facilities within existing utility right-of-way.

Status

We submitted an application for a Permit to Construct to the California Public Utilities Commission (CPUC) in October 2013.

Project Timeline

  • October 2008 – We filed Advice Letter 2272-E, notifying the CPUC of the proposed construction of this project.
  • February 2009 – CPUC issued Executive Director’s Action Resolution E-4225, finding that this project qualified for an exemption from CPUC permitting requirements.
  • March 2010 – CPUC issued Commission Resolution E-4243, affirming the findings of Resolution E-4225.
  • October 2010 – We commenced construction on the project.
  • November 2011 – CPUC issued Decision 11-11-019, ordering a cease to all construction activity, and directing us to file a Permit to Construct application to complete the project.
  • October 2013 – We submitted an application for a Permit to Construct to the CPUC.
  • June 2015 – CPUC issued a Draft Environmental Impact Report (EIR) on the project.

Contact Information

If you have questions or comments about this project or would like to be added to the project mailing list, please contact us.

Rudy Gonzales
Region Manager
1-805-497-5616
Rudolph.Gonzales@sce.com.