How to Submit a Claim to SCE

If you have suffered a loss or damage due to recent service interruption, and believe we may be responsible, you may submit a claim. How to submit your claim >

We investigate and evaluate each claim individually, and our policy is to respond promptly.

Long Beach Update

As of 4:20 a.m. today, we are in the process of reconnecting customers to the network who have been on generator power.

Affected customers may experience temporary outages during this process. We thank customers for their patience as we work to restore them to the network as safely and efficiently as possible. We encourage customers in Long Beach to make every effort to conserve use of electricity as we continue to return the system to its full operational capacity.

We will reopen our distribution center at 925 Locust at 8 a.m. today to distribute food, ice and water. The safety of the public and our crews remain our highest priority. We thank the city of Long Beach for its cooperation and for the safety efforts of first responders in the Long Beach Fire and Police departments. Get the latest update >

Leatherneck Substation Project

Upgrading Infrastructure Near Twentynine Palms

This project will provide a new substation aboard the Marine Corps Air Ground Combat Center, and will include improvements to the nearby Carodean and Hi Desert substations.

Neighboring Communities

Twentynine Palms and adjacent unincorporated areas

Project Details

  • A new 115/33kV substation
  • Upgrades to both the existing Carodean Substation (located on Two Mile Road and Lear Avenue) and the Hi Desert Substation (located near Dortin Place next to Highway 62).
  • Overbuilding* existing 33kV lines between these two substations and the new Leatherneck Substation with new 115kV sub-transmission lines (approximately 9 miles in length), to be supported with a combination of new lightweight and tubular steel poles.


*Overbuilding means installing a new circuit above existing facilities. It may require replacing existing poles with new poles along the same pole route.

Status

Project is complete.

Project Timeline

  • May, 2011: We filed project application with the CPUC
  • September, 2011: CPUC approval of project
  • June, 2012: Began construction on military base
  • July, 2012: Began construction off military base
  • January, 2014: Construction was complete. Leatherneck Substation entered service.

Contact Information

If you have questions or comments about this projector would like to be added to the project mailing list, please contact us. Try our toll-free Project Information Line: 1-888-226-9916. Or contact our local staff.

From Twentynine Palms:

Jennifer Cusack
Region Manager
1-760-202-4211
Jennifer.Cusack@sce.com

From elsewhere in San Bernardino County:

Beverly Powell
Region Manager
1-909-307-6742
Beverly.Powell@sce.com

Interested in working with SCE as a supplier? Learn more.