CORRECTION
In-Person Public Participation Hearings (PPHs) is on 4/10  in Long Beach.
Date: Wednesday, April 10, 2024 
Time: 2:00 p.m. and 6:00 p.m.
Location: Recreation Park Community Center, 4900 E. 7th St., Long Beach, CA 90804. 

The previous notice for the in-person SCE Public Participation Hearings before the California Public Utilities Commission for the 2025 General Rate Case (A.23-05-010) had an incorrect date. For complete information click here.

January 2019 Rate Changes

January 2019 Rate Changes

Effective January 1, 2019, the rate components listed below changed as follows.

  • Transmission – for all rates
  • Distribution – for some Residential rates and for the Commercial “R” rates.
  • PPPC – for all rates
  • TOTCA – for all rates
  • CIA – for applicable Residential rates
  • SCE Gen – for some rates (RTP hourly rates did not change)
  • DWR Bond Charge – for all rates
  • DWR Energy Credit – for all rates
  • PCIA – for all rates
  • CARE Surcharge
  • CARE Discount % – for all TOU CARE rates
  • FERA Discount % – for all TOU FERA rates
  • State Tax factor – for all rates
  • Green Rate factors – for all applicable rates

California Alternate Rates for Energy (CARE)

SCE’s current and revised CARE Surcharge and CARE Discount Percentage are listed below:

Rate Component $/kWh Rate or Percentage Prior to January 1, 2019 $/kWh Rate or Percentage as of January 1, 2019
Domestic CARE Surcharge* 0.00508 0.00507
CARE Discount for Commercial Accounts 27.6% 27.7%

*The CARE Surcharge rate is shown in dollars/kWh. All non-CARE, non-Street Lighting customers pay this same amount on an equal dollars/kWh basis.

Family Electric Rate Assistance (FERA)

SCE’s current and revised FERA Discount Percentage are listed below:

Rate Component $/kWh Rate or Percentage Prior to January 1, 2019 $/kWh Rate or Percentage as of January 1, 2019
FERA Discount 12% 18%