Home > Environment > Transmission Projects > Projects By County > San Bernardino County > Falcon Ridge Substation Project

Transmission Projects - Projects By County

Falcon Ridge Substation Project

The cities of Fontana and Rialto, along with surrounding areas including Rancho Cucamonga and Devore in San Bernardino County, have experienced rapid growth in recent years and will continue to do so as new land use developments are planned for the region. The electrical infrastructure that currently serves the area is approaching its capacity to provide reliable electricity during periods of high demand. Construction of Falcon Ridge Substation will enable Southern California Edison (SCE) to continue providing safe and reliable electrical service to meet this need.

The Falcon Ridge Substation project will:

  • Provide increased electrical capacity and delivery to serve the region’s growing need.
  • Improve electrical distribution system flexibility and increase reliability by providing the ability to transfer electrical demand between other distribution substations within the region.
  • Enhance the ability to serve future electrical demand through the construction of the Falcon Ridge Substation.

at-a-Glance

Project description

SCE proposes to construct a 66/12 kilovolt (kV) substation in the north Fontana area, 66 kilovolt (kV) electrical subtransmission lines into the proposed substation and 12 kV underground electrical distribution lines delivering electricity from the proposed substation to customers as part of the project.

Communities within the project area

Fontana, Rialto and Rancho Cucamonga

Project status

This project is currently under regulatory review.

Proposed in-service date: 2014

Timeline - Anticipated Project Schedule
Summer 2010 SCE hosted project open house
December 2010 SCE filed project application with the California Public Utilities Commission (CPUC)
January 2012 Draft Environmental Impact Report released by the CPUC
February 2012 CPUC conducts public scoping meeting
Summer/Fall 2012 CPUC decision is expected
Fal 2013 Start of construction
Summer 2014 Proposed In-Service Date

Project Contact Information

For Fontana and Rialto:
Christian Nelson
SCE Region Manager
(909) 930-8495
christian.nelson@sce.com

For unincorporated San Bernardino County:
Beverly Powell
SCE Region Manager
(909) 307-6742