Home > Environment > Transmission Projects > Current Projects > El Casco System Project

Transmission Projects - Current Projects

El Casco System Project

El Casco System Project

Simulation of subtransmission line looking west from Highland Springs Road.

Customer demand for electricity in the northwest Riverside County area will soon exceed the capacity of SCE's local and regional electric system. To address this growing demand and improve the reliability of the electric system, SCE is constructing the El Casco System Project, which consists of a new substation and the upgrade of an existing electric line.

at-a-Glance

Project description

Build the new El Casco substation and upgrade 15.4 miles of electric lines.

Communities Potentially Affected

Banning, Beaumont, Yucaipa and adjacent areas of unincorporated Riverside County.

Project status

Construction is scheduled to begin September 2009.

Proposed in-service date

November 2010.

Timeline - Anticipated Project Schedule
December 2008 The project was approved by the CPUC.
September 2009 Construction is scheduled to begin.
November 2010 Construction is expected to be complete.

Project Contact Information

For general information on the project, call the toll-free project hotline at
(866) 464-2005.

For area specific questions or if you would like to be added to the project mailing list, please contact:

For Banning and Beaumont:
Lin Juniper
SCE Region Manager
(760) 202-4231

For Cherry Valley, Calimesa and Yucaipa:
Beverly Powell
SCE Region Manager
(909) 307-6742

For unincorporated Riverside County:
Louis Davis
SCE Region Manager
(909) 930-8446




FOR OVER 100 YEARS...LIFE. POWERED BY EDISON.