WDAT Generator Interconnection Process Reform

Queue Cluster Windows Schedule Applicable to Large Generator Interconnection Requests

In accordance with SCE’s WDAT CLGIP, Interconnection Requests Queue Cluster Windows will be opening (and closing) within the following schedule:

Anticipated Queue Schedule
Cluster Opening Date Closing Date
Queue Cluster Window 1 Mon Aug 11, 2008 Fri Jul 31, 2009
Queue Cluster Window 2 Thu Oct 01, 2009 Sun Jan 31, 2010
Queue Cluster Window 3 Thu Apr 01, 2010 Sat Jul 31, 2010

Each calendar year thereafter will have two Queue Cluster Windows with opening and closing dates established by SCE and published on this website. SCE will timely publish any changes to the Queue Cluster Window intervals and opening or closing dates on this website.

SCE - WDAT Generator Interconnection Requests (PDF)

Interconnection Study Reports for SCE-WDAT Generator - Interconnection Requests Greater Than 20 MW (PDF)

SCE is currently performing a review of the reports that were previously posted on this site. An updated posting will be available soon.